Kitchen and primary bath remodel in Ann Arbor, MI

Featured project. Ann Arbor, Michigan

A kitchen, a primary bath and new floors, done as one project

This Ann Arbor project bundled three remodels into one signed proposal. We gutted the kitchen and took out its soffits, rebuilt the upstairs primary bathroom around a bigger walk-in shower, laid new vinyl plank across the first floor and refinished the hardwood upstairs.

LocationAnn Arbor, Michigan
ProjectKitchen, primary bath and floors
RoomsKitchen, bath, living room and stairs
InvestmentAbout $177,000

A kitchen and primary bath remodel in Ann Arbor

Plenty of Ann Arbor houses have good bones and tired rooms. This one had a kitchen boxed in by soffits, a primary shower the owner wanted bigger and first floor flooring that was ready to go. The owner asked for a full kitchen and bathroom remodel plus new floors, which made it a whole house job in everything but the name.

Will wrote the proposal, and it was approved at about $148,200. Ten change orders followed as the owner added lighting, extended the backsplash, replaced a subfloor section and took a post out of the living room. The final came to about $177,000, and every added dollar went through a signed change order before the work started.

That’s how our whole home remodeling works when a project grows. You see the price of each addition in writing, you approve it or you don’t, and the budget never moves without your signature.

What we built

A kitchen without the soffits

Remodeled kitchen in an Ann Arbor home with dark lower cabinets, marble-look counters, an island with seating and colored glass pendants
The kitchen

Dark base cabinets, warm uppers and a long island

We gutted the kitchen: cabinets, counters, flooring, backsplash and the soffits above the old uppers. Where the soffits came out, the framing was reworked and the drywall patched and painted. Then the new kitchen cabinets went in, with a long island for seating and marble-look counters from our countertop contractor.

Green, blue and red glass pendant lights hanging over a marble-look kitchen island in Ann Arbor
The lighting

Pendants, trim lights and under-cabinet LEDs

The electrical plan added LED trim lighting, new GFCI outlets and under-cabinet lights that run on both a switch and a sensor. A later change order hung the three glass pendants over the island, and another brought new fixtures to the living room. Our page on kitchen lighting covers how we layer task and accent light in a room like this.

The details

A backsplash that grew twice

The tiled backsplash was extended twice after the proposal was signed, each time by change order, and the kitchen window was replaced in the same pass. Our crew installed the cabinets, trim and hardware and set the backsplash tile, while electrical, plumbing, HVAC and countertop contractors handled their trades under our project management. Our guide to countertops and backsplash materials covers the choices behind a wall like this one.

Marble-look island counter in front of a range wall with tile backsplash run to the ceiling in an Ann Arbor kitchen
Marble-look counters on the island, with the range wall beyond.
Stainless refrigerator set between tall wood pantry cabinets in a remodeled Ann Arbor kitchen
The refrigerator sits between tall wood pantry cabinets.

Why the soffits came out

Soffits can hide ductwork, pipes or nothing at all, and you rarely know which until they’re opened. Here, removing them meant reframing, drywall repair and coordinating the HVAC changes before a single cabinet was hung. It’s the same kind of thinking that goes into opening up a floor plan, just at the scale of one ceiling.

Upstairs

A primary bath built around a walk-in shower

Upstairs, the primary bathroom was gutted. Tile, toilet, vanity, mirror and closet doors all came out, along with the wall that limited the shower. We reframed that wall to widen the opening, installed GoBoard waterproofing and tiled a walk-in shower with a niche and a pebble floor. Our glass contractor finished it with frameless shower glass and a door.

Primary bathroom vanity room in Ann Arbor with a wood vanity, round mirror and pebble tile floor leading toward the bedroom
The layout

A doorway moved and a vanity room tiled

Before construction started, a change order moved the bathroom doorway so it opens between the vanity room and the bedroom, and added tile to the vanity room floor. The finish list included a new, taller toilet, the vanity, towel bars, closet shelving and new closet doors. A new vent fan handles the bathroom ventilation a tiled shower needs.

Walk-in tiled shower with blue-gray stone-look wall tile, a niche and a pebble floor in an Ann Arbor primary bathroom
The walk-in shower, with a niche and a pebble floor.
Double wood vanity with two round mirrors and a pebble tile floor in a remodeled Ann Arbor primary bathroom
A double wood vanity with round mirrors in the vanity room.

Floors and stairs

New floors downstairs, refinished hardwood up

Every room on the first floor got new vinyl plank once the old flooring came out, and a subfloor section that needed it was replaced by change order. If you’re weighing materials for a kitchen, our guide to kitchen flooring compares the options. Upstairs, the existing hardwood was sanded and refinished instead of replaced.

Staircase with white risers, wood treads and a wood handrail leading to the refinished upstairs in an Ann Arbor home
The stairs up to the refinished hardwood.
Black horizontal bar stair railing with a wood cap at the top of the stairs in an Ann Arbor home
A black bar railing with a wood cap at the top landing.

A post out of the living room

The living room had a post standing in the middle of it. We installed an LVL beam to carry that load, took the post out and repaired and finished the drywall around the new beam. Structural changes like this one are planned during preconstruction in our design-build process, so the beam is sized and priced before anything is cut.

The scope, line by line

This is what the approved proposal and its change orders covered, grouped by trade. Contracted trades were electrical, plumbing, HVAC, countertop and glass installers.

Planning

Plans, permits and selections

In-house plans, permitting and inspections, and selections with the project manager.

Kitchen

Full gut and soffit removal

New cabinets, contracted countertops, tile backsplash extended twice and a replaced window.

Electrical

Lighting and outlets

LED trim lights, GFCI outlets, under-cabinet lights, island pendants and living room fixtures.

Bathroom

Walk-in tiled shower

Shower wall reframed, GoBoard, wall and floor tile, frameless glass and a new vent fan.

Layout

Doorway moved

Bathroom door relocated between the vanity room and bedroom, vanity room tiled.

Structure

LVL beam in the living room

New beam carries the load so the post could come out, drywall finished.

Floors

Vinyl plank and refinished hardwood

First floor vinyl plank, a subfloor section replaced, upstairs hardwood refinished.

Questions we hear

Remodeling more than one room at once

Can you remodel a kitchen and a bathroom at the same time?

Yes, and it often costs less in disruption than doing them a year apart. One proposal, one project manager and one permit process cover both rooms. Start with our kitchen remodeling and primary bathroom remodel pages to see what each room usually involves.

What happens to the price when I add work?

Every addition gets its own written change order with its own price, and nothing is built until you approve it. This project had ten, from lighting to a structural beam. If a larger scope stretches the budget, our renovation financing page walks through the options.

Planning more than one room at once?

Tell us which rooms are on your list. We’ll walk the house, price each room line by line and show you what it costs to do them together or one at a time.